Most of the The functionality necessary to provide the collection and storage of data in the electronic signature process has already been completed as part of the database model supporting NPS. The additional tasks, resources, and time needed to meet the specific goals of the electronic signature project are list below. e-logbook certification]

The functionality necessary to process submitted e-logbook data and generate receipts was developed during the PIFSC's electronic reporting pilot program which was conducted from 1998-2003. As a result of the pilot, and of this e-signature design effort, requirements have matured and some changes are required. The implementation plan for these changes is:

Task/Milestone

Due Date

Staffing

develop specifications for required changes

 

 

develop test plan

 

 

implement changes

 

 

execute test plan and correct defects

 

 

production readiness review

 

 

go live