Activity

Resources

Non-recurring
Cost

Recurring
Cost

Certification programprocess: development through deployment

 

  Project funded by FIS

$55,000

 

Certification programprocess: maintenance and operations

  1 man week/year - Manager

  

$3,000

Certification assessment per application (quantity estimated as 1)

 

 2)

4 man weeks - Manager
4 man weeks - Technical

$24,000

 

Data import program for portable media: development through deployment

 

  1 man month - Programmer

$12,000

 

Data import program for portable media: maintenance and operations

  1 man week/year - Programmer

  

$3,000

Email interface program for email submissions: development through deployment

 

  1 man month - Programmer

$12,000

 

Email interface program for email submissions: maintenance and operations

  1 man week/year - Programmer

  

$3,000